Stormwater and traffic management
Along the entire stretch, we decommissioned the existing pipelines, either by removing them or filling them with concrete. We reconnected and restored existing road drains and additionally installed service connections and 120 new inspection and property boundary maintenance holes for the future construction sites planned along the 1,680 m long project area.
To manage and receive rainwater from the southern part of Lundtoftegårdsvej, we also established a pumping station, designed to connect the new pipelines to the existing system.
Finally, we restored the road, cycle path and pavement, including the installation of kerbstones, cobblestone paving, lamp posts, asphalt surfacing, lane markings, pedestrian crossings and traffic symbols.
Our traffic management, divided into multiple phases, was a critical aspect of our bid and the execution of the project.